Facts 7:
1. That the contents of para 1 of the Grounds of appeal are denied as the award in question has been passed after consideration of all the submissions made by Appellant as well as Respondent. 2. That, the contents of Para 2 of the grounds of the Appeal are denied being incorrect. The work of the Respondent was stopped by the officials of the Appellant on 05.05.2016 and vide letter dated 09.05.2016, the Respondent informed the Appellant to sort out the matter as soon as possible so that the work can be resumed. It was also stated in the letter that the Respondent shall not be held liable for any delay caused due to conduct of the Bank Officials. At this juncture it becomes pertinent to mention here that the construction work of the Respondent was stopped by the Appellant Officials due to use of different Brands of Building Material as mentioned in the tender documents and in this regard a letter dated 18.04.2016 was issued by the Project Architect of the Appellant to the Respondent aski...